Fraunhofer HHI 2018 MPW Schedule

 

Fraunhofer HHI InP Tx-Rx platform

Tx-Rx platform with passives, MMIs, AWGs, pin detectors, SOAs, DFB lasers, DBR gratings, polarization converters / splitters, spot size converters and thermo-optic phase shifters. As from October 2016, HHI has switched to MPW scheduled every three months as follows:

Run ID

Design Submission Deadline

Mask Tape-Out

Expected Delivery

Status

HHI05

15-Oct-2016

23-Oct-2016

Mid-June-2017

Delivered

HHI06

15-Jan-2017

22-Jan-2017

End-Sept-2017

Delivered

HHI07

16-Apr-2017

23-Apr-2017

Mid-Apr-2018

Delivered

HHI08

16-Jul-2017

23-Jul-2017

End-July-2018

In fab

HHI09

21-Oct-2017

30-Oct-2017

End-July-2018

In fab

HHI10

15-Jan-2018

22-Jan-2018

End-July-2018

In fab

HHI11

16-Apr-2018

22-Apr-2018

22-Oct-2018

Fabrication started

HHI12

16-Jul-2018

22-Jul-2018

22-Jan-2019

Open for registration

HHI13

15-Oct-2018

21-Oct-2018

21-Apr-2019

Open for registration